Posted on: November 29, 2018

NCDOT Delays Gasters Creek Bridge Reopening

ncdot

DECEMBER 14TH UPDATE

The NC Department of Transportation reports that due to cold and wet weather, the Gasters Creek bridge will not open today as previously scheduled. The contractor anticipates the bridge will open by the end of the month.

NCDOT's Travel Information Management System has been updated to reflect the new goal.

NOVEMBER 28TH UPDATE

NCDOT's Travel Information Management System has been updated to reflect the new goal. (Link: https://tims.ncdot.gov/TIMS/IncidentDetail.aspx?id=526378)

The N.C. Department of Transportation has announced a two-week delay for the Gasters Creek bridge reopening. The new date is Friday, December 14.

Originally closed in June and scheduled to reopen on November 15, the bridge was rescheduled to open on November 30 at 5:00 p.m. However, the NCDOT contractor performing the work estimates the company will need at least two weeks to complete the last remaining work.

Still left to be done is paving, curb and gutter concrete work, shoulder construction, and final pavement marking. The contractor notes that the cold temperatures may affect their timeline. 

Follow the project in NCDOT's travel information management system for further updates.